Queen’s Grant High School

Gymnasium & Performing Arts Center

Girl with vest in front of theatre sign

Unlocking Excellence:

Building A Bright Future Together

Heading Separator

At Queen’s Grant High School, the Gym/Performing Arts Center is not just a structure; it’s a symbol of our commitment to excellence in education and the arts. It’s a space where our students will thrive, and our community will come together. Your continued support is invaluable as we move closer to turning this visioninto reality.

Join us on this remarkable journey to build a brighter future for Queen’s Grant High School. Together, we’ll unlock excellence and create lasting opportunities for our students. Stay tuned for more updates as we make progress towards our goal.

Legacy for Tomorrow:

Be a Part of the Story with Our Engraved Brick Campaign!

Heading Separator

We invite your invaluable support to help us reach our ambitious $5 million fundraising goal for the Queen’s Grant Gymnasium/ Performing Arts Center Engraved Brick campaign. This call extends to all members of our extended Queen’s Grant family, including past, present, and future families, as well as local businesses and individuals who share our vision. Your generous contribution will play a pivotal role in realizing the long-awaited expansion of Queen’s Grant High School. This expansion promises a multitude of benefits, from hosting athletic events and practices on our campus to creating additional classroom space for gym, art, music, and dance classes. It will also provide us with the capacity to host major events such as proms, homecomings, student performances, and graduations. The positive impact of this expansion extends far beyond our current students, benefiting future students from Queen’s Grant Community School and Matthews Charter, who receive enrollment preference. Your support helps pave the way for an even brighter educational future for all.

Fundraising Brick

Progress

Heading Separator

Our architect and contractor have been hard at work, bringing us one step closer to realizing this incredible addition to our campus. We’re excited to provide you with the following update on our journey to construct this cutting-edge Gym/Performing Arts Center.

Timeline

Heading Separator
February 8
February 20
March 7
Mid-April
Mid-May
Mid-June

February 8

Mint Hill public hearing

February 20

Mint Hill Planning Board review and recommendation

March 7

Mint Hill Mayor and Commissioners will either approve or decline

Mid-April

Final site drawings will be completed. Contractor will send out for quotes, which takes a minimum of 30 days. Contractor will also start obtaining building permits during this time, anticipating breaking ground by mid-June

Mid-May

Contractor will submit completed quote and contract to QGHS for legal review, with anticipated review/approval at the QG June Board meeting. Contractor’s completed project quote is also sent to the bank for the appraisal process

Mid-June

Bank requires a copy of executed contract between the Board and Contractor. Closing date/groundbreaking is to be determined but anticipated to be mid-June